Skip to main content
Commercial sitework crew performing mass excavation and grading on a Kansas City construction site

Commercial Sitework Contractor in Kansas City

From raw ground to finished concrete — one contractor, one schedule, zero coordination failures.

★★★★★ Commercial & Industrial · In Service Since 2015
Call (816) 339-8133
What Sitework Actually Is

The Phase That Decides Whether Your Project Finishes on Time — or Doesn’t

Sitework is the umbrella term for everything that happens between raw ground and the moment a foundation can be poured. On most commercial projects in the Kansas City metro, it represents 15–25% of total construction cost — and 100% of the schedule risk if any phase is sequenced wrong.

Industry terms like site preparation, earthwork, and civil construction all describe pieces of the same picture. Sitework is the broadest correct term for the entire phase. Here’s what it actually includes:

Pre-construction land clearing and permitting phase on a Kansas City commercial site
Phase One

Pre-Con & Clearing

Geotech, civil engineering, MoDNR or KDHE permits, 811 locates, demolition, clearing, grubbing, and topsoil strip — before anything else moves.

Mass excavation earthwork phase with hydraulic excavator in the Kansas City metro
Phase Two

Earthwork

Mass excavation, cut/fill balance, 8-inch lifts compacted to 95% modified proctor, KC clay moisture-conditioned to ±2% of optimum.

Utility trenching phase with open trench and trench box on a Kansas City project
Phase Three

Grading & Utilities

Rough grade to ±0.1 ft, proof roll with loaded tandem dump truck, then sanitary, storm, water below frost line, electric, gas, and telecom.

Fine grading and sub-base preparation phase before concrete pour on a Kansas City commercial pad
Phase Four

Sub-Base & Concrete

Fine grade to ±0.05 ft, AB-3 or Type 5 base rock compacted and density-verified, then the concrete pour — by the same crew, no handoff gap.

An excavation-only contractor can handle most of it. A concrete-only contractor can handle none of it. The gap between those two specialties is where most Kansas City commercial projects lose days, dollars, and warranties.

Our entire model exists to close that gap — by being both companies at the same time, on the same crew, under the same contract.

Heavy excavation equipment on a Kansas City commercial construction site — CAT excavator and loader moving earth
The Single-Source Advantage

One Contractor for Sitework and Concrete. No Handoff. No Gap.

The traditional commercial construction model splits sitework and concrete between two separate subcontractors. The sitework sub finishes rough grading, demobilizes, and bills out. A 1–3 week gap opens up while the concrete sub schedules and mobilizes. By the time the concrete crew arrives, the sub-base has settled, eroded, or lost moisture — and you’re paying to re-grade a pad you already paid to prepare. The slab gets poured on a foundation nobody fully owns, and when it cracks twelve months later, the fingers point in both directions while the owner writes the repair check.

5–10
Business days saved per pad
1–3 wk
Handoff gap eliminated
95%
Modified proctor verified
1
Warranty, raw ground to slab
01 · Site Grading

Site Grading

Rough grading to ±0.1 ft, fine grading to ±0.05 ft, and finish grading with GPS machine control. Drainage engineering that actually works on Wymore-Ladoga clay — minimum 5% slope for the first 10 feet off any foundation, because code minimum is not enough for KC clay.

  • Rough grading to ±0.1 ft tolerance
  • Fine grading to ±0.05 ft with GPS machine control
  • Building pad proof-rolling with loaded tandem dump truck
  • Drainage grading engineered for KC clay, not generic spec
  • Sub-base prep with AB-3 (Kansas) or Type 5 base rock (Missouri)
Full Grading Details →
Site grading with CAT motor grader on Kansas City commercial construction pad
Mass excavation with large hydraulic excavator on Kansas City commercial construction site
02 · Mass & Precision Excavation

Mass & Precision Excavation

Bulk earthwork for 1–10 acre commercial pads, precision excavation for footings and foundations, and rock excavation through Bethany Falls and Argentine limestone south of 135th Street. Everything dug, classified, placed, and verified by the same crew that pours the concrete on top of it.

  • Mass excavation and cut/fill balance
  • Rock excavation through southern JoCo limestone (3–15 ft depth)
  • Structural fill placed in 8-inch lifts to 95% modified proctor
  • Nuclear density gauge verification at depth, not just surface
  • OSHA 29 CFR 1926 Subpart P competent person on every dig
Full Excavation Details →

Bidding a Commercial Project?

Send us your civil plans and geotech report. Detailed bid returned within 5 business days.

Call (816) 339-8133
03 · Land Clearing

Land Clearing & Grubbing

Raw-land clearing, tree removal, grubbing below finish grade, stump extraction, debris haul-off, and topsoil strip and stockpile for commercial, industrial, and subdivision development across the KC metro. Nothing left in the ground to rot under a future slab.

  • Tree removal and selective clearing
  • Root systems grubbed below finish grade
  • Stump grinding and extraction
  • Debris haul-off and wood recycling
  • Topsoil stripped, stockpiled, and preserved for final stabilization
Full Land Clearing Details →
Land clearing and tree removal on a Kansas City commercial development site
Utility trenching with trench box shoring for sanitary sewer installation in Kansas City
04 · Utility Trenching

Utility Trenching

Sanitary, storm, water, electric, gas, and telecom — trenched, bedded, backfilled, and pressure-tested by our own crew. Water mains below the 36-inch frost line. Tracer wire on every non-metallic run. Missouri One-Call and Kansas One-Call 811 compliance before anyone touches a shovel.

  • Sanitary and storm sewer installation
  • Water mains below 36-inch KC frost line
  • Electric, gas, and telecom conduit coordination
  • Tracer wire and locatable warning tape on every run
  • Pressure testing before close-out, every time
Full Utility Trenching Details →
Who You’re Hiring

Single-Source. Two States. No Coordination Failures.

11
Years Serving KC
377+
Projects Completed
MO·KS
Two-State Licensed
OSHA
Subpart P Trained
05 · Demolition

Concrete & Structure Demolition

Concrete slab, structural, and selective demolition with on-site concrete recycling. KCMO and Johnson County permits handled in-house. Debris hauled off and, wherever possible, crushed and reused as base rock on the same project — because hauling clean concrete to a landfill is a waste of money and a waste of a material.

  • Concrete slab and flatwork demolition
  • Structural and selective demolition
  • On-site concrete crushing and recycling
  • KCMO and Johnson County demolition permits in-house
  • Asbestos and environmental abatement coordination
Full Demolition Details →
Concrete slab demolition with hydraulic breaker on a Kansas City redevelopment site
SWPPP-compliant silt fence and stone construction entrance on a Kansas City commercial site
06 · Erosion Control & SWPPP

Erosion Control & SWPPP

NPDES Construction Stormwater compliance through MoDNR on the Missouri side and KDHE KEIMS on the Kansas side. BMP installation, weekly inspection logs, BMP maintenance, and Notice of Termination filed at 70% vegetative cover. Written by people who actually read the permit.

  • NPDES Construction Stormwater filing (MoDNR or KDHE)
  • SWPPP preparation and on-site binder maintenance
  • Silt fence, wattles, inlet protection, construction entrance
  • Weekly inspections and rain-event documentation
  • Notice of Termination at 70% vegetative cover closeout
Full Erosion Control Details →
How Sitework Works

The 8 Phases of a Kansas City Commercial Pad

For a typical 1–3 acre commercial pad in the KC metro, this sequence runs 4–10 weeks of active work depending on volume, weather, and utility complexity.

01

Pre-Construction & Permitting

Geotechnical review, civil engineering coordination, survey, pre-construction meeting, and permit filings. KCMO grading permits run 4–6 weeks. MoDNR Land Disturbance Permit needs 30+ days. KDHE NPDES through the KEIMS portal runs 10–20 business days with a $90 application fee. We start the paperwork the day a project is awarded so plan review runs concurrently with engineering.

02

Mobilization & Erosion Control

Stone construction entrance, perimeter silt fence, inlet protection, and concrete washout area — installed BEFORE any other ground disturbance, per NPDES Construction Stormwater requirements. This sequence is non-negotiable for both MoDNR and KDHE inspectors, and skipping it is the fastest way to earn a stop-work order in the KC metro.

03

Clearing, Grubbing & Demolition

Vegetation removed, root systems grubbed below finish grade, existing structures and slabs demolished, debris hauled off, and topsoil stripped to its full organic depth and stockpiled on-site for final stabilization. Nothing organic gets buried under future concrete on our projects.

04

Mass Excavation & Earthwork

Cut/fill executed per the grading plan. KC clay placed in 8-inch lifts, moisture-conditioned to within 2% of optimum (typically 16–20%), and compacted with sheepsfoot rollers to 95% modified proctor for structural fill, 90% for general fill. Nuclear density gauge testing on every lift, at depth. Rock excavation south of 135th Street handled with hoe-ram when Bethany Falls limestone appears.

05

Rough Grading & Proof Roll

Building pads and drive lanes brought to within ±0.1 ft of plan grade. Drainage paths cut and verified. The pad is proof-rolled with a loaded tandem dump truck, and any soft spots are over-excavated and replaced with structural fill before utility installation begins.

06

Underground Utilities

Sanitary sewer first (deepest), then storm sewer, water line below the 36-inch frost line, then electric, gas, and telecom. Granular bedding stone, pipe-zone backfill, tracer wire on all non-metallic pipe, locatable warning tape, and pressure testing on water and sewer before backfill is closed.

07

Sub-Base Preparation

Fine grading to ±0.05 ft. Geotextile fabric over expansive clay where the geotech specifies it. 4–8 inches of AB-3 aggregate base (Kansas) or Type 5 base rock (Missouri), placed and compacted to 95% modified proctor with a vibratory roller. Density verified before any forms go down.

08

The Handoff — Concrete Construction

This is where the traditional sitework-to-concrete handoff fails on most KC commercial projects, and where our single-source model wins. The same crew that prepared and density-tested the sub-base sets forms and pours the slab. No demobilization. No 1–3 week gap. No re-grading. Schedule compresses 5–10 business days on a typical 1–3 acre commercial pad.

The Differentiator
Kansas City Geotechnical Reality

The Soil You’re Building On — and Why It Matters to Your Slab

The dominant soil across Jackson, Johnson, and Clay counties is the Wymore-Ladoga complex. The Wymore series is classified as CH (fat clay) under the Unified Soil Classification System and A-7-6 under the AASHTO classification used by the Missouri and Kansas DOTs. The Ladoga series, which interfingers with Wymore across the metro, is classified as CL (lean clay) and A-6 AASHTO. Both run 60 to 80 percent clay content in most areas. Both carry a “very high” shrink-swell rating. Both behave very differently from the granular soils that form the textbook examples in most engineering courses.

The Missouri River bluffs and parts of Leavenworth and Wyandotte counties are mantled with loess deposits classified as ML silt — highly erodible, easy to grade dry, and prone to collapse when saturated. The Missouri River alluvial belt through Riverside, Parkville, and the Fairfax industrial district holds SM and SC silty/clayey sand: it drains beautifully and compacts well, but it can liquefy under hydrostatic pressure in a hundred-year flood event. Southern Johnson County sits over Bethany Falls and Argentine limestone formations that can appear at three to fifteen feet of depth. Northern Johnson County and most of Jackson County have deeper clay overburden with limestone at ten to thirty-plus feet. Platte County river bottom pushes bedrock down to forty to eighty-plus feet.

Compaction of KC clay requires holding moisture within two percent of optimum — typically sixteen to twenty percent for modified proctor — and lifts cannot exceed eight inches uncompacted. The swell factor when KC clay is excavated runs twenty-five to thirty-five percent: every 1,000 bank cubic yards you cut becomes 1,250 to 1,350 loose cubic yards on the haul trucks. Grades set in fall move when spring rains arrive. Grades set in spring move when summer drying begins. Setting a building pad in November and pouring a slab in March without re-verifying compaction is one of the most common causes of slab failure in this market — and the kind of failure an excavation-only contractor will never see, because they will already be off the project by the time the concrete cracks.

Soil Data — KC Metro
Wymore Series
USCS: CH (Fat Clay)
AASHTO: A-7-6
Shrink-Swell: Very High
Ladoga Series
USCS: CL (Lean Clay)
AASHTO: A-6
Shrink-Swell: High
Loess (River Bluffs)
USCS: ML (Silt)
AASHTO: A-4
Collapse risk when saturated
Alluvial (MO River)
USCS: SM / SC
Drains well, liquefaction risk
KC Metro Baseline
Frost depth: 30–36 in
Swell factor: 1.25–1.35
Compaction target: 95% mod proctor
Jackson, Johnson, Clay counties

The Clay Belt

Wymore-Ladoga fat and lean clay, 60–80% clay content, very high shrink-swell. The default soil beneath most of the KC metro.

Leavenworth, Wyandotte, MO River

The River Bluffs

Loess deposits (ML silt). Stable dry, highly erodible and collapsible when saturated. Careful dewatering required.

Southern Johnson County

The Limestone Belt

Bethany Falls and Argentine limestone at 3–15 ft depth. Rock excavation contingency on every project south of 135th.

Equipment & Capabilities

The Fleet We Bring to Every Kansas City Job Site

Hydraulic Excavators used on Kansas City Concrete Contractors commercial sitework projects
Hydraulic Excavators
CAT 320, 330 · Komatsu PC210 · Deere 350G
Dozers & Scrapers used on Kansas City Concrete Contractors commercial sitework projects
Dozers & Scrapers
CAT D6, D8 · Deere 850K · CAT 621K scraper
Wheel Loaders used on Kansas City Concrete Contractors commercial sitework projects
Wheel Loaders
CAT 950, 966 · Deere 644
Motor Graders (GPS) used on Kansas City Concrete Contractors commercial sitework projects
Motor Graders (GPS)
CAT 140M with GPS machine control
Compaction Rollers used on Kansas City Concrete Contractors commercial sitework projects
Compaction Rollers
Bomag BW211D · sheepsfoot rollers
Trenchers & Skid Steers used on Kansas City Concrete Contractors commercial sitework projects
Trenchers & Skid Steers
Ditch Witch, Vermeer · CAT 259D · Deere 333G

Our fleet runs on owned and leased equipment sized to the project. We match the machine to the scope: compact excavators and skid steers for urban infill and tight-access commercial, full-size CAT 320 and 330 excavators and D6/D8 dozers for mass earthwork on retail and industrial pads, CAT 140M motor graders with GPS machine control for fine grading to ±0.05 ft on parking lot and warehouse sub-grades, and nuclear density gauge testing at depth on every compacted lift — performed by our own crew, not a third-party lab that shows up after the fact.

Two-State Regulatory Reality

The Kansas City Metro Spans Two States. Your Permit Path Depends on Which Side.

Missouri Side

MoDNR

  • NPDES Land Disturbance Permit Filed through MoDNR online portal for any project over 1 acre. 30+ day review window.
  • PE Supervision Not required at state level, though many MO cities require PE-stamped plans as a city condition.
  • KCMO City Grading Permit 4–6 weeks of agency review — the longest in the metro.
  • 811 Utility Locates Missouri One-Call, 2 business days minimum notice, ticket valid 14 days.
Kansas Side

KDHE

  • NPDES Construction Stormwater Filed through KDHE KEIMS electronic system. $90 application fee. 10–20 business day review.
  • PE Supervision Required Kansas-licensed Professional Engineer must supervise the SWPPP.
  • City Grading Permits Overland Park 2–3 weeks (fastest). Olathe/Lenexa/Shawnee 2–4 weeks.
  • 811 Utility Locates Kansas One-Call, 2 business days minimum notice, ticket valid 14 days.
Applies Everywhere

OSHA 29 CFR 1926 Subpart P — Excavation Safety

Federal OSHA Subpart P requires soil classification (Type A, B, or C), mandates a designated competent person on-site for any excavation, and requires protective systems — sloping, benching, shoring, or trench boxes — in any trench five feet deep or greater. Our crew runs a competent person on every dig that triggers Subpart P, and trench boxes are standard equipment on our utility installations. Applies to both sides of the state line without exception.

Sitework Cost Overview

What Sitework Actually Costs in the Kansas City Metro

Scope Unit Typical KC Range Notes
Mass Excavation (common soil) per BCY $8–15 Wymore-Ladoga clay, on-site
Mass Excavation w/ Haul-Off per BCY $14–22 25–35% swell factor
Rock Excavation per BCY $25–50+ Bethany Falls / Argentine limestone
Rough Grading per SF $0.40–0.90 ±0.1 ft tolerance, GPS
Fine Grading per SF $0.30–0.60 ±0.05 ft tolerance
Sub-Base (AB-3 / Type 5) per SF $1.50–3.50 4–8 in, compacted to 95%
Utility Trenching per LF $15–45 Depth and pipe dependent
Land Clearing per acre $1,500–12,000 Density of growth dependent
Concrete Slab Demo per SF $4–10 Includes recycling
SWPPP (plan + BMPs + closeout) per project $2,000–8,000 MoDNR or KDHE filing
Compaction Testing per test $150–300 Nuclear density gauge, ASTM D6938
Mobilization per project $1,500–5,000 Commercial scope

BCY vs LCY vs CCY — The Measurements That Matter

BCY (bank cubic yard) is dirt in place, before it’s disturbed. LCY (loose cubic yard) is the same dirt after it’s excavated and dumped loosely on a truck. CCY (compacted cubic yard) is that same dirt after it’s placed, moisture-conditioned, and compacted in a structural fill. KC clay has a 25–35% swell factor from BCY to LCY, meaning every 1,000 BCY removed becomes 1,250–1,350 LCY on haul trucks. That matters for hauling cost. Shrinkage factor from LCY back to CCY as it’s compacted into fill is another 10–15%. Bids that don’t differentiate between these three measurements are bids written by people who haven’t actually moved KC dirt.

Project Types

What We Build For

🍳

Restaurant Pads

Quick-service and fast-casual builds on 0.5–1 acre infill sites with aggressive schedules.

🛒

Retail Strip Centers

1–3 acre pads, parking lots, and curb-and-gutter for shopping centers and pad-site retail.

🏭

Warehouse & Industrial

3–10 acre pads with FF/FL flatness specs and heavy-axle truck loading design.

🏢

Multi-Family & Mixed-Use

2–5 acre sites with structured parking and complex stormwater detention.

Church & School Sites

Campus development with parking, ADA walks, drop-off lanes, and play surfaces.

🚑

Office & Medical Campus

Professional and medical office with detention basins and patient drop-off geometry.

🚗

Parking Lots & Curb

Stand-alone lot construction, reconstruction, milling, and sub-base remediation.

🏠

Subdivisions

10–50 lot residential subdivisions: mass earthwork, streets, utility mains, lot certification.

Request a Commercial Bid

Bidding a Project? Send Us Your Plans.

Send us your civil plans, geotech report, SWPPP scope, and any bonding requirements. We return a detailed bid that breaks out earthwork, utilities, sub-base, and concrete as discrete line items — so your project manager can compare apples to apples across multiple subs.

  • Typical bid turnaround: 5 business days
  • Line-item breakdown: earthwork, utilities, sub-base, concrete
  • Bonded work · MO and KS licensed
  • MoDNR and KDHE permit filings handled in-house

Start Your Bid Request

Click below to open the bid request form. Provide the project address, scope, acreage, timeline, and upload any plans you have — we’ll respond within one business day to confirm receipt.

or call directly
Sitework FAQ

What Kansas City GCs and Developers Ask Us Most

How long does sitework take for a typical commercial pad in Kansas City?
For a 1–3 acre commercial pad in the KC metro, active sitework runs 4–10 weeks depending on cut/fill volume, utility complexity, weather, and rock contingency. Pre-construction permitting adds 4–8 weeks in front of that, with KCMO grading permits running the longest at 4–6 weeks of agency review and KDHE NPDES permits clearing in 10–20 business days through the KEIMS portal. Spring projects in the KC metro should budget 40–50% weather days through May, which averages 5.2 inches of rainfall — the wettest month of the year. Our single-source model compresses the back end of the schedule by 5–10 business days because the same crew transitions directly from sub-base prep into the concrete pour without a demobilization gap.
What does sitework cost per cubic yard in Kansas City?
Mass excavation in common KC clay soils runs $8–15 per bank cubic yard (BCY). Add haul-off through the Wymore-Ladoga clay belt and budgets typically land at $14–22 per BCY because the swell factor is 25–35%, meaning every 1,000 BCY you remove becomes 1,250–1,350 loose cubic yards (LCY) on the trucks. Rock excavation through Bethany Falls or Argentine limestone south of 135th Street jumps to $25–50+ per BCY depending on hardness and ripping versus hammering. Every bid we issue separates earthwork, utilities, sub-base, and concrete as discrete line items so a Kansas City GC can compare apples to apples across multiple subs.
Do I need a SWPPP for my Kansas City project?
If your project disturbs one acre or more of ground anywhere in the KC metro, you are federally required to obtain NPDES Construction Stormwater coverage and operate under a Stormwater Pollution Prevention Plan. On the Missouri side, that means a Land Disturbance Permit through MoDNR (Missouri Department of Natural Resources), filed via the state online portal with a 30+ day review window. On the Kansas side, NPDES coverage runs through the KDHE (Kansas Department of Health and Environment) KEIMS electronic system with a $90 application fee and a 10–20 business day review. Both states require the SWPPP to be on-site, weekly inspection logs maintained, and a Notice of Termination filed at project closeout once 70% permanent vegetative cover is achieved.
How long does a KCMO grading permit actually take?
Realistically, 4–6 weeks of agency review once a complete application is submitted to Kansas City, Missouri — and that is the longest grading permit timeline of any major jurisdiction in the KC metro. By comparison, Overland Park typically clears grading permits in 2–3 weeks, and Olathe and Lee's Summit run 2–4 weeks. We treat KCMO permitting as a parallel-path activity, filing the application the day a project is awarded so plan review runs concurrently with geotech, civil engineering finalization, and SWPPP preparation. Anyone telling you a KCMO grading permit will be in hand in two weeks is either not being honest or has not actually filed one recently.
What is the difference between MoDNR and KDHE stormwater permits?
Both administer NPDES Construction Stormwater coverage under the federal Clean Water Act, but the procedures and standards differ. MoDNR (Missouri) issues a Land Disturbance Permit through a state online portal, allows 30+ days for review, and does not require a Kansas-licensed Professional Engineer to supervise the SWPPP at the state level — though many Missouri cities require PE-stamped plans as a city condition. KDHE (Kansas) processes NPDES coverage exclusively through the KEIMS electronic system, charges a $90 application fee, runs a 10–20 business day review, and explicitly requires a Kansas-licensed PE to supervise the SWPPP. Our team files in both states routinely and knows the inspector expectations on each side of the state line.
Will my Olathe or southern Johnson County project hit limestone bedrock?
Probably yes, and it should be in the bid. Southern Johnson County — Olathe, Gardner, Spring Hill, and the corridor south of 135th Street — sits over Bethany Falls and Argentine limestone formations that commonly appear at 3–15 feet of depth. Northern Johnson County and most of Jackson County have deeper clay overburden with limestone at 10–30+ feet. Platte County river bottom in Riverside and Parkville pushes bedrock down to 40–80+ feet. Any responsible bid for an Olathe commercial pad should carry a rock excavation contingency line item because even a thorough geotech with three or four boring logs cannot guarantee the formation depth across an entire site.
Can you handle the concrete after the sitework is done?
Yes — and that is the entire reason Kansas City Concrete Contractors exists as a single-source contractor instead of an excavation-only company. The same crew that strips topsoil, excavates, places and compacts structural fill, installs utilities, and prepares the sub-base also sets forms and pours the concrete on top of it. Whether the finished product is a parking lot, a warehouse floor, a foundation, a curb-and-gutter run, or a retaining wall footing, there is no handoff, no demobilization, no second mobilization fee, and one warranty covering the work from raw ground through finished slab. This is the most important sentence on this page for any KC general contractor reading it.
When is the best time of year for sitework in Kansas City?
June through September is the optimal window for sitework in the KC metro. Soil moisture is manageable, rain delays are shorter, and KC clay holds compaction within the 2% moisture window required for 95% modified proctor. May is the wettest month of the year in Kansas City, averaging 5.2 inches of rain, and any spring earthwork schedule should budget 40–50% weather days. Winter earthwork is technically possible but expensive — frost penetrates 30–36 inches in a typical KC winter, halting active grading and pushing utility crews into frozen-ground premiums. The most cost-effective sequence we see in this market is clearing in April, mass earthwork through summer, concrete poured by October, and SWPPP closeout in the fall growing window for permanent vegetative cover.
What is OSHA 29 CFR 1926 Subpart P and do you comply?
Subpart P is the federal OSHA standard governing excavation safety on construction sites. It requires soil classification (Type A, B, or C — KC clay is generally Type B or Type C depending on moisture and disturbance history), mandates a designated competent person on-site for any excavation, and requires protective systems — sloping, benching, shoring, or trench boxes — in any trench five feet deep or greater. Our crew operates with a competent person on every dig that triggers Subpart P, and trench boxes are standard equipment on our utility installations. This is not optional, and on a Kansas City commercial project it is one of the first things a thorough GC will verify before mobilization.
Can you bid a Kansas City project bonded?
Yes. We bid bonded commercial projects across the KC metro for general contractors, developers, municipal procurement, and federal work that requires payment and performance bonds. Send us the plans, the geotech report, the SWPPP scope, and the bond requirements and we will return a detailed bid that breaks out earthwork, utilities, sub-base, and concrete as separate line items — typically within 5 business days of receiving a complete plan set.

Send Us Your Plans.

One contractor. Raw ground to finished concrete. Detailed bid in 5 business days.

(816) 339-8133
Call Now